Which of the following best conveys the essence of learning curves?


A) As the number of repetitions increases,time per unit increases.
B) As the number of repetitions decreases,time per unit increases.
C) As the number of repetitions increases,time per unit decreases.
D) As the number of repetitions increases,time per unit remains constant.
E) As the number of repetitions increases,time per unit doubles.

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

To use the table of learning-curve coefficients,you must specify ________ and ________.

Correct Answer

verifed

verified

the learning curve r...

View Answer

A learning curve:


A) plots man-hours per dollar versus time.
B) is mathematically described by a parabola.
C) should be plotted on polar coordinate graph paper.
D) is based on the premise that organizations learn from experience.
E) follows a normal distribution.

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is a limitation of the use of learning curves?


A) Change in personnel,design,or procedure leave the learning curve unchanged.
B) Learning curves are applicable to services as well as to manufacturing.
C) The culture of the workplace may alter the learning curve.
D) Direct labor and indirect labor follow the same learning curves.
E) Applications of learning curves are of tactical,not strategic,importance.

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

The second unit of production took 9 hours.If the learning curve is 90% how long did the first unit take?


A) 9 hours
B) 10 hours
C) 8.1 hours
D) 8.5 hours
E) none of the above

F) A) and C)
G) D) and E)

Correct Answer

verifed

verified

The fundamental premise underlying learning curve analysis is that:


A) tasks can be easily learned in organizations.
B) organizations and people become better at their tasks as the tasks are repeated.
C) learning takes place when people in organizations change.
D) total labor costs decrease as the number of production units increases.
E) doubling output cuts labor requirements per unit in half.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

The learning curve may not be permanent; it can be disrupted by changes in process,personnel,or product.

A) True
B) False

Correct Answer

verifed

verified

A contractor builds large ships for the Department of Defense.A recent contract called for 12 amphibious landing platforms.It was originally estimated that the first of these would cost $1 billion and that 80 percent learning would be appropriate.In fact,the first ship cost $1.6 billion and the second $1.12 billion.What is the revised learning curve? What will be the total cost of the twelve ships? Is it higher or lower than the original estimate? If the defense department cuts the contract from 12 ships to 9,what happens to the average cost per ship?

Correct Answer

verifed

verified

The original estimates called for $1 bil...

View Answer

A defense contractor has just started producing engines for a new government contract.The first engine took 800 hours to produce.If the learning curve is 80%,how long will it take to produce the first 20 engines?


A) less than or equal to 1000 hours
B) from 1000 to 8000 hours
C) from 8000 to 8500 hours
D) from 8500 to 10000 hours
E) 10,000 or more hours

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Your firm has expertise with a special type of hand-finished furniture.The learning curve is known to be 82%.If the first piece of furniture took 6 hours,how long will it take to make the second? How long will it take to make the fourth?

Correct Answer

verifed

verified

Use the doubling approach.The ...

View Answer

The learning curve rate is:


A) the percentage of time it will take to make each unit when the production rate doubles.
B) the log-log of the annual rate change divided by the average unit cost.
C) always based on constant value dollars.
D) only considered valid after one year of data is accumulated.
E) equal to at least 75%.

F) C) and E)
G) A) and D)

Correct Answer

verifed

verified

The formula approach to learning curve calculations allows us to determine the hours required for any unit.

A) True
B) False

Correct Answer

verifed

verified

A project manager bases his time and labor estimates on a learning curve of 86%.The actual learning curve turns out to be 89%.The manager,because of the decreased learning,will complete his project in more time and with more labor use than his estimate suggested.

A) True
B) False

Correct Answer

verifed

verified

If the learning curve for a process is 100 percent,then each unit in a series of units will have the same labor requirements.

A) True
B) False

Correct Answer

verifed

verified

Suppose that there are two products with the same first product time.However,product A has an improvement rate of 10% while product B has an improvement rate of 20%.How much longer will it take to make the 10th unit of product A compared to product B?


A) Both will have the identical time for the 10th unit.
B) A will take 48% more time.
C) A will take 48% less time.
D) A will take 23% less time.
E) none of the above

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

A manager is trying to estimate the appropriate learning curve for a certain job.The manager notes that the first four units had a total time of 30 minutes.Which learning curve would yield approximately this result if the first unit took 9 minutes? (Use Table E.3.)


A) 0.70
B) 0.75
C) 0.80
D) 0.85
E) 0.90

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

A 90% learning curve implies that each time the production volume is doubled,the direct time per unit is reduced to 90% of its previous value.

A) True
B) False

Correct Answer

verifed

verified

Why do different organizations have different learning curves?

Correct Answer

verifed

verified

The rate of learning varies de...

View Answer

You are about to undertake the manufacture of a labor-intensive electronics component.The first unit took 300 hours.You are not sure whether the learning curve is 70% or 80%.The initial phase of the contract calls for 6 of these components. a.How much time will it take to complete all six at 70% learning? b.How much time will it take to complete all six at 80% learning?

Correct Answer

verifed

verified

From Table E.3,70 percent lear...

View Answer

What cautions are in order when using learning curves?

Correct Answer

verifed

verified

The cautions when using learning curves ...

View Answer